APC SBPSU10K15F-WP Datasheet


Add to my manuals

advertisement

APC SBPSU10K15F-WP Datasheet | Manualzz

Installation

MGE™ Galaxy™ 3500 and Smart-UPS

®

System Maintenance Bypass Panel

VT

Wall Mount

10-15 kVA 208 V, 10-30 kVA 208 V

IMPORTANT SAFETY INSTRUCTIONS

- SAVE THESE INSTRUCTIONS

Warning: ALL safety instructions in the Safety Sheet

(990-2940) must be read, understood and followed when installing the UPS system. Failure to do so could result in equipment damage, serious injury, or death.

Heavy: APC recommends that two people mount the

Maintenance Bypass Panel (MBP) to the wall—one person to lift and hold the enclosure, and a second person to secure it to the wall.

Caution: All electrical power and power control wiring must be installed by a qualified electrician, and must comply with local and national regulations for maximum power rating.

990-3603A-001 *990-3603A3/2010

Caution: Operation and maintenance must only be performed by qualified personnel.

Product Overview

Front view (interior)

N

PE/G

N

 Q1 input breaker

 Q3 bypass breaker. A

Philips screwdriver is required to unlock Q3.

 Q2 output breaker

 Knockouts for conduits

 Control terminal block

 Output neutral busbar

 PE/ground busbar

 Mains input

 Critical load

 Input neutral busbar

Site Planning

Note: APC strongly recommends mounting the MBP to a minimum 20 mm (3/4 in) thick plywood board or similar solid backing that has approximate dimensions.

Note: Ensure that the wall area you selected to install the

MBP is structurally sound and able to support the size and weight of the unit.

Note: Protect the MBP at all times from excessive moisture, construction dirt, corrosive elements, or other contaminants.

Note: When choosing a location to mount the MBP, consider the need for easy access to all breakers and internal components.

Space requirements

Refer to the following figure to determine the space requirements for installing the MBP. Consult local codes for any additional requirements. Ideally, install the MBP in a location close to the UPS.

Minimum front clearance

559 mm

(22 in)

457 mm

(18 in)

Minimum floor clearance

Prepare for cables

Note: All external cable connections with the UPS and mains must be made on-site. External cables are not supplied with the equipment.

Note: All control wire connections between the UPS and the

MBP must be made on-site. Control wires are not supplied with the equipment.

Create knockouts for cable access

Note: You can create knockouts for cable access either before or after you have mounted the MBP to the wall. APC recommends creating all necessary knockouts prior to mounting the MBP to the wall.

 Open the front door.

 Use a knockout punch to create appropriate-sized holes for two inch and one inch cable conduits in either the top or bottom plate of the MBP.

Mount the MBP to the wall

 Mount the plywood

(or other backing) to the wall by using appropriate hardware for the type of wall used.

 457 mm (18 in) 

 Measure and mark the four mounting hole locations on the wall.

 Drill holes in each of the four marked locations.

 Lift the MBP, position it against the backing and line it up with the four mounting holes. Secure the MBP with four M8 (3/8 in) bolts and flat washers.

Connect Power Cables

See Also: For information on grounding, see manual 990-

3606.

Input N

Mains input

L1 L2 L3

X001

PE/G

L1

L2

L3

L1

L2

L3

N

L1

L2

L3

N

1......8

Q1

UPS input

Q3

Q2

UPS output

X010

Output N

Critical load

L1 L2 L3

X004

Route the cables through the top or the bottom of the MBP.

 Connect the mains input cables ( L1, L2, L3, N, G) to the mains input terminals (X001), the input neutral, and the ground busbar.

 Connect the UPS input cables (L1, L2, L3, N, G) to the right side of the Q1 breaker, the input neutral, and the ground busbar.

 Connect the UPS output cables (L1, L2, L3, N) to the left side of the

Q2 breaker, the output neutral, and the ground busbar.

 Connect the cables from the critical load (L1, L2, L3, N, G) to the critical load terminals (X004), the output neutral, and the ground busbar.

Connect Communication Cables

Note: For the connection of a Q3 auxiliary signal, use a 1-

1.5 mm 2

( 18-16 AWG) copper wire.

 Connect a copper wire between the UPS (J106 port 5) and the MBP

(X010 port 7 on the control terminal block).

 Connect a copper wire between the UPS (J106 port

6) and the MBP (X010 port

8 on the control terminal block).

 

Specifications

Electrical

SBPSU10K15F-WP

10-15 kVA

SBPSU20K30F-WP

20-30 kVA

Nom. input voltage

Nom. output voltage

208/220V 4W+GND

208/220V 4W+GND

208/220V 4W+GND

208/220V 4W+GND

Circuit breaker rating 60A 125A

Wiring (only use copper conductors suitable for at least 75°C)

Maximum cable size 50 mm

2

(1/0 AWG) 150 mm

2

(300 Kcmil)

System output/ UPS output cable

25 mm 2 (4 AWG) 50 mm 2 (1 AWG)

System input/UPS input cable

25 mm

2

(4 AWG) 50 mm

2

(1 AWG)

Physical

Dimensions

(H × W × D)

Shipping dimensions

(H × W × D)

Weight

Shipping weight

617 x 561 x 216 mm

(24.3 x 22.1 x 8.5 in)

719 x 667 x 330 mm

(28.3 x 26.25 x 13 in)

23.6 kg (52 lbs)

25.9 kg (57 lbs)

617 x 561 x 216 mm

(24.3 x 22.1 x 8.5 in)

719 x 667 x 330 mm

(28.3 x 26.25 x 13 in)

28.1 kg (62 lbs)

30.4 kg (67 lbs)

2

Environmental

Operating environment Indoor use only, protect from water and conductive contaminates

Operating temperature

Humidity

0° to 40°C (32° to 104°F)

0 to 95%, non-condensing

Torque value

Terminal blocks

(M6 x 15 stud)

Busbars M6

Breaker T1

Breaker T3

6.89 Nm (61 lbs in)

11.3 Nm (100 lbs in)

5 Nm (45 lbs in)

9 Nm (80 lbs in)

Contact Information

For local, country-specific centers: go to www.apc.com/support/ contact.

Appendix

MBP diagram

3

advertisement

Was this manual useful for you? Yes No
Thank you for your participation!

* Your assessment is very important for improving the workof artificial intelligence, which forms the content of this project

Related manuals

Download PDF

advertisement