1. LENOX ROAD
EAST94TH
STREET
PLAY YARD
EXIST. MASONRY BLDG
# OF STORIES - 4
COURTYARD
SIDEWALK
SIDEWALK
EXIST. WROUGHT IRON FENCE
EXIST.WROUGHTIRON
FENCE
EXIST. CHAIN-LINK
FENCE
EXIST. CHAIN-LINK
FENCE
PROPERTY
LINE (TYP)
EXIST. CURB
EXIST.
CURB
RAMP
RAMP
I.S.
252K
EXIST.
WROUGHT
IRONFENCE
SIDEWALK
EAST93RD
STREET
EXIST.
CURB
EXIST.
CHAIN-LINK
FENCE
PROPERTY
LINE
(TYP)
125 BROAD STREET, NEW YORK, NY 10004
PHONE: 212-377-8400, FAX: 212-377-8410
SCA Design Manager:
D016040
Design No: Facility Code:
K 252 04/14/2016
Date:
Project:
of 64
Sheets in DOB Set:
Drawing No.:
Drawing Title:
Address:
Stanley Dahir, R.A., Director, Quality Control & Construction Support
Elan R. Abneri, P.E., Senior Director, Design Consultant Management
Architecture & Engineering
Designer:
Checked by:
Drawn by:
Project Architect/Engineer:
1084 LENOX ROAD, BROOKLYN, NY 11212
E. Bruce Barrett, R.A. LEED A.P., Vice President
Consultants:
Stacey Spann-Thom, Director, Operations Support
George D. Roussey, P.E., LEED A.P., Director, Technical Standards
Discipline Lead:
of 85
Sheets in Contract Set:
Board of Trustees
Curtis A. Harris
President & CEO
Lorraine Grillo
Emily A. Youssouf
IT IS A VIOLATION OF THE STATE EDUCATION LAW SECTION 7209 (2)
FOR ANY PERSON TO ALTER AN ITEM IN ANY WAY UNLESS SUCH
PERSON IS ACTING UNDER THE DIRECTION OF A LICENSED
PROFESSIONAL ENGINEER, AND THE ENGINEER STAMPS SUCH
CHANGES
IS 252K
BOILER REPLACEMENT
CLIMATE CONTROL
Lot # 37BLOCK # 4669
Key Plan:
EAST95THSTREET
PLAY YARD
I.S. 252K
EAST94THSTREET
LENOX ROAD
COURT
YARD
RevisionDateNo.
Sheet Number Sheet Title Sheet in
BCC
Sheet in
CS
GENERAL
T001 COVER SHEET 01 01
T002
LIST OF DWGS, NOTES, INSPECT, LOCATION PLAN AND SITE
PLAN
02 02
T003 INSPECTIONS, D.O.B. NOTES, SUMMARY OF WORK 03 03
T004 SITE PLAN - TEMPORARY BOILER AND FUEL OIL TANK PLAN 04 04
ENERGY ANALYSIS
EN001 ENERGY ANALYSIS SHEET 1 05 05
EN002 ENERGY ANALYSIS SHEET 2 06 06
ENVIRONMENTAL
H101 ASBESTOS REMOVAL - GENERAL NOTES -- 07
H102 ASBESTOS REMOVAL PLAN BASEMENT -- 08
H103 ASBESTOS REMOVAL - ROOF PLAN -- 09
ARCHITECTURAL
A001 ABBREVIATIONS, LEGEND AND MOUNTING HEIGHTS 07 10
A030 SITE REMOVAL PLAN 08 11
A035 SITE PLAN 09 12
A036 COURT YARD EGRESS PLAN 10 13
A061 CELLAR SELECTIVE REMOVAL PLAN 11 14
A062 SELECTIVE REMOVAL PARTIAL ELEVATIONS 12 15
A101 CELLAR PLAN 13 16
A102 ROOF PLAN 14 17
A201 SOUTH ELEVATION 15 18
A202 PARTIAL ELEVATIONS 16 19
A401 DETAIL SHEET 1 17 20
A402 DETAIL SHEET 2 18 21
A403 GAS YARD ENLARGED PLAN AND FENCE DETAILS 19 22
A410 FIRESTOPPING DETAILS 20 23
A411 BOILER ACCESS PLATFORM PLAN AND SECTION 21 24
A412 BOILER ACCESS PLATFORM PLAN AND SECTION 21A 24A
A801 CELLAR REFLECTED CEILING PLAN 22 25
A920 WINDOW AND LOUVERS SCHEDULE, ELEVATIONS AND DETAILS 23 26
A921 WINDOW DETAILS 24 27
A922 WINDOW GUARDS 25 28
A930
STRUCTURAL
S001 GENERAL NOTES AND ABBREVIATIONS 27 30
FO051 FOUNDATION PLAN - REMOVAL 28 31
S101 FOUNDATION PARTIAL PLAN I 29 32
S201 SECTIONS AND DETAILS 30 33
MECHANICAL
M001 HVAC GENERAL NOTES, SYMBOLS AND ABBREVIATIONS 31 34
M002 HVAC SCHEDULES 32 35
M051 CELLAR SELECTIVE REMOVALS 33 36
M052 FUEL OIL SYSTEM SELECTIVE REMOVAL 34 37
M101 HVAC CELLAR FLOOR PLAN 35 38
M102 HVAC FIRST FLOOR PLAN 36 39
M103 HVAC SECOND FLOOR PLAN 37 40
M104 HVAC THIRD FLOOR PLAN 38 41
M105 HVAC FOURTH FLOOR PLAN 39 42
M106 HVAC ROOF PLAN 40 43
M107 FUEL OIL SYSTEM PROPOSED PLAN 41 44
M301 HVAC CELLAR PARTIAL PLAN 42 45
M302 HVAC SECTIONS 43 46
M401 HVAC BOILER PLANT FLOW DIAGRAM 44 47
M402 HVAC NETWORK RISER DIAGRAM 45 48
M403 HVAC AIR COMPRESSOR RISER DIAGRAM 46 49
M404 HVAC GAS LEAK DETECTION CONTROL WIRING DIAGRAM 47 50
M405 HVAC FUEL OIL RISER DIAGRAM 48 51
M406 HVAC CONTROL SCHEMATICS 49 52
M501 HVAC DETAILS SHEET 1 50 53
M502 HVAC DETAILS SHEET 2 51 54
M503 HVAC DETAILS SHEET 3 52 55
M504 HVAC DETAILS SHEET 4 53 56
M505 HVAC DETAILS SHEET 5 54 57
M601 HVAC EQUIPMENT RIGGING PATH 55 58
PLUMBING
P001 P&D SYMBOLS, ABBREVIATIONS, NOTES 56 59
P002 PLUMBING SCHEDULES 57 60
P061 PLUMBING SELECTIVE REMOVAL PLAN - CELLAR 58 61
P101 PLUMBING CELLAR FLOOR PLAN AND FIRST FLOOR PART PLAN 59 62
P301 PLUMBING FLOW DIAGRAMS 60 63
P302 PLUMBING GAS RISER DIAGRAM 61 64
P401 PLUMBING DETAILS 62 65
ELECTRICAL
E001 ELECTRICAL SYMBOLS, ABBREVIATIONS, NOTES -- 66
E002 ELECTRICAL LIGHTNING PROTECTION PLAN -- 67
E061 ELECTRICAL CELLAR LIGHTING REMOVAL PLAN -- 68
E062 ELECTRICAL CELLAR POWER REMOVAL PLAN -- 69
E101 ELECTRICAL CELLAR LIGHTING PLAN -- 70
E201 ELECTRICAL CELLAR PLAN - POWER SYSTEMS -- 71
E202 ELECTRICAL FIRST FLOOR PLAN - POWER SYSTEMS -- 72
E203 ELECTRICAL SECOND FLOOR PLAN - POWER SYSTEMS -- 73
E204 ELECTRICAL THIRD FLOOR PLAN - POWER SYSTEMS -- 74
E205 ELECTRICAL FOURTH FLOOR PLAN - POWER SYSTEMS -- 75
E401 ELECTRICAL CELLAR PARTIAL PLAN -- 76
E501 ELECTRICAL ONE LINE DIAGRAM -- 77
E601 ELECTRICAL LIGHTING FIXTURE SCHEDULE -- 78
E701 ELECTRICAL DETAILS SHEET 1 -- 79
E702 ELECTRICAL DETAILS SHEET 2 -- 80
FIRE ALARM
FA001 FIRE ALARM SYMBOLS & LEGENDS ABBREVIATIONS AND NOTES 03 81
FA101 FIRE ALARM CELLAR PLAN 04 82
FA102 FIRE ALARM FIRST FLOOR PLAN 05 83
FA201 FIRE ALARM RISER DIAGRAM 06 84
FA401 FIRE ALARM DETAILS 07 85
THE FOLLOWING NOTES SHALL APPLY THROUGHOUT. EXCEPTIONS ARE SPECIFICALLY NOTED ON
DRAWINGS.
1. THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND CONDITIONS OF THE SITE AND
BUILDING.
2. THE CONTRACTOR SHALL, UNLESS OTHERWISE PROVIDED IN THE CONTRACT DOCUMENTS, SECURE
AND PAY FOR REQUIRED INSPECTIONS, PERMIT(S), FEES, LICENSE AND INSPECTIONS NECESSARY
FOR THE PROPER EXECUTION OF THE WORK.
3. APPLICATION FOR CONSTRUCTION PERMITS SHALL BE PROCESSED THRU THE BUILDING CODE
COMPLIANCE DIVISION OF THE AUTHORITY.
4. COORDINATION OF WORK UNDER THIS CONTRACT SHALL BE MAINTAINED TO ENSURE THE QUALITY
AND TIMELY COMPLETION OF THE WORK/PROJECT.
5. THE CONTRACTOR SHALL PERFORM CUTTING AND PATCHING REQUIRED TO COMPLETE THE WORK
OR TO MAKE ITS PARTS FIT TOGETHER PROPERLY WITHOUT COMPROMISING THE QUALITY OF THE
WORK.
6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ADEQUATELY BRACING AND PROTECTING WORK
DURING CONSTRUCTION AGAINST DAMAGE, BREAKAGE, COLLAPSE, DISTORTIONS, AND OFF
ALIGNMENTS ACCORDING TO CODES AND STANDARDS OF GOOD PRACTICE.
7. THE TERM "FINISH FLOOR" SHALL MEAN THE NORMAL FINISHED SURFACE OF THE FLOOR LEVEL.
ELEVATIONS GIVEN FOR EXISTING BUILDINGS ARE TO FINISHED FLOOR. THE CONTRACTOR SHALL
FIELD VERIFY ELEVATIONS FOR EXISTING STRUCTURES PRIOR TO THE COMMENCEMENT OF WORK.
8. THE CONTRACTOR SHALL CORRECT ANY VARIATIONS IN FLOOR ELEVATIONS CREATED BY THE
REMOVAL OF PARTITIONS AND/OR FOR THE INSTALLATION OF NEW DOOR OPENINGS.
9. THE CONTRACTOR SHALL NOT CONSTRUCT, UNLESS OTHERWISE NOTED, INTERIOR CMU PARTITION
WALLS TO FULL HEIGHT UNTIL PIPES, DUCTS, ETC.. ARE IN PLACE.
10. THE CONTRACTOR SHALL PATCH AND REPAIR ALL FLOORS, WALLS CEILINGS, ETC.. DAMAGED OR
EXPOSED DUE TO WORK OR REMOVALS AND FINISH TO MATCH ADJOINING SURFACES.
11. VERTICAL SHAFTS SHALL HAVE A MINIMUM FIRE RATING OF 2-HOURS UNLESS REQUIRED
OTHERWISE BY CODES DUE TO OCCUPANCY ADJACENCIES.
12. THE DISTANCE FROM DOOR JAMBS TO ADJACENT PARTITIONS, BUILT-IN FURNITURE OR OTHER
FURNISHINGS SHALL NOT BE LESS THAN 6" UNLESS OTHERWISE NOTED ON THE DRAWINGS.
13. ELECTRICAL INDICATIONS ON ARCHITECTURAL DRAWINGS ARE FOR LOCATION PURPOSES ONLY.
14. UNLESS OTHERWISE NOTED, INTERIOR BRICK WALLS SHALL BE INSTALLED IN A RUNNING BOND.
15. WHERE MANUFACTURES' NAMES AND PRODUCT NUMBERS ARE INDICATED ON THE DRAWINGS, IT
SHALL BE CONSTRUED TO MEAN THE ESTABLISHING OF QUALITY AND PERFORMANCE STANDARDS
OF SUCH ITEMS. OTHER PRODUCTS MUST BE SUBMITTED TO THE ARCHITECT FOR APPROVAL
BEFORE THEY SHALL BE DEEMED EQUAL.
16. FIRESTOPPING SHALL BE INSTALLED AT PENETRATIONS OF FIRE-RATED CONSTRUCTION AS PER
SPECIFICATIONS. FIRESTOPPING MATERIALS ARE TO BE APPROPRIATE FOR, AND BE PART OF A
LISTED AND LABELED ASSEMBLY IN ACCORDANCE WITH THE BUILDING CODE OR HAVE OTCR OR MEA
APPROVAL.
17. LOCATIONS AND DIMENSIONS OF CONCRETE EQUIPMENT PADS IN THESE DRAWINGS ARE
APPROXIMATE. FINAL LOCATIONS AND SIZES MUST BE COORDINATED WITH THE EQUIPMENT
MANUFACTURER AND ARE SUBJECT TO APPROVAL WITH THE EQUIPMENT SHOP DRAWINGS. THERE
SHALL BE NO ADDITIONAL MONIES PAID FOR INCREASE IN SIZE OF PAD DUE TO DIFFERENCE IN SIZE
OF THE EQUIPMENT CHOSEN BY THE CONTRACTOR FROM THAT OF MODEL NUMBER/SIZE INDICATED
IN CONTRACT DOCUMENTS.
18. DIMENSIONS ON PLANS ARE INDICATED FROM SURFACE TO SURFACE BETWEEN WALLS, PARTITIONS
AND OTHER ITEMS EXCLUSIVE OF FINISHES.
19. SIZE OF MASONRY UNITS AND WOOD MEMBERS ON PLANS, BUILDING ELEVATIONS AND SECTIONS
ARE SHOWN AS NOMINAL SIZE.
20. DRAWINGS ARE NOT TO BE SCALED. USE DIMENSIONS ONLY. DIMENSIONS AND CONDITIONS SHOWN
AND ASSUMED ON THE DRAWINGS MUST BE VERIFIED AT THE SITE BY THE CONTRACTOR BEFORE
ORDERING ANY MATERIAL OR DOING ANY WORK. ANY DISCREPANCIES IN THE DRAWINGS AND
SPECIFICATIONS SHALL BE REPORTED TO THE AUTHORITY. NO CHANGE IN DRAWINGS OR
SPECIFICATIONS IS PERMISSIBLE WITHOUT THE WRITTEN CONSENT OF THE ARCHITECT/ENGINEER.
NO WORK SHALL PROCEED UNTIL SUCH DISCREPANCY HAS BEEN RECTIFIED.
21. WORK ON THESE DRAWINGS SHALL BE CONSIDERED NEW WORK WHETHER STATED OR NOT EXCEPT
WHERE SPECIFICALLY NOTED AS "EXISTING".
22. THE CONTRACTOR SHALL DISCONNECT AND/OR REMOVE ANY EXISTING PLUMBING, ELECTRICAL
FIXTURES, WIRE CONDUITS, OR OTHER WORK WHICH MIGHT INTERFERE WITH THE WORK OF THIS
CONTRACT. AFTER NEW WORK IS COMPLETED, THE DISCONNECTED OR REMOVED ITEMS SHALL BE
REINSTALLED BY THE CONTRACTOR AT THE SAME LOCATION OR AT NEW LOCATION AS DIRECTED.
FURNISH NECESSARY NEW MATERIALS/HARDWARE FOR COMPLETION OF WORK.
23. THE CONTRACTOR SHALL PATCH AND REPAIR DAMAGED OR EXPOSED SURFACES DUE TO
CONTRACT WORK. NEWLY INSTALLED, PATCHED WORK AND AFFECTED AREAS SHALL BE PAINTED.
PAINTING WORK SHALL BE PERFORMED TO COVER THE ENTIRE HORIZONTAL OR VERTICAL SURFACE
TO THE CLOSEST CORNER IN FOUR DIRECTIONS. COLORS TO BE APPROVED BY ARCHITECT PRIOR
TO APPLICATION.
24. THE CONTRACTOR SHALL FURNISH AND INSTALL NEW MATERIALS AT NO ADDITIONAL COST TO THE
AUTHORITY FOR THE FOLLOWING CONDITIONS:
a) EXISTING WORK THAT HAS BEEN REMOVED OR DAMAGED IN ORDER TO PERFORM THE CONTRACT
WORK.
b) TO FURNISH THE WORK OF THIS CONTRACT IN WORKMANLIKE MANNER.
25. THE CONTRACTOR SHALL INCLUDE PREPARATION AND ASSOCIATED SUPPLEMENTARY WORK TO
PROVIDE A COMPLETE AND FINISHED INSTALLATION.
26. PROVIDE GUARDS, RAILS, BARRICADES, FENCES, SIDEWALK SHEDS, CATCH PLATFORMS, DECKING,
NIGHT LIGHTING, ETC., AS REQUIRED BY THE NEW YORK CITY BUILDING CODE, SECTION 1901.5 AND
AS REQUIRED TO PROVIDE ADEQUATE PROTECTION. ALSO, COMPLY WITH SECTION S01900 OF THE
SPECIFICATION.
27. THE CONTRACTOR SHALL MAINTAIN FREE AND UNOBSTRUCTED ACCESS FROM ADJACENT SPACES
INTO THE EXISTING FIRE STAIRS TO OUTSIDE OF THE BUILDING AT ALL TIMES.
28. THE CONTRACTOR SHALL KEEP WORK SITE FREE FROM DEBRIS AND ACCUMULATED REFUSE, AND
SHALL HAVE SOLE RESPONSIBILITY FOR PROTECTING DANGEROUS AREAS FROM ENTRY BY
UNAUTHORIZED PARTIES. SITE SHALL BE LEFT BROOM CLEAN AT THE END OF EACH WORKING DAY.
29. WHERE INDICATED OR REQUIRED TO PERFORM THE WORK, PACK, PROTECT AND RELOCATE BOOKS,
MATERIALS, FURNITURE, CABINETS, ETC. TO DESIGNATED LOCATIONS WITHIN THE BUILDING AND
RETURN ITEMS UPON COMPLETION OF WORK OR WHEN DIRECTED BY THE AUTHORITY.
30. THERE WILL BE NO CHANGE IN USE, EGRESS OR OCCUPANCY BECAUSE OF THE WORK OF THIS
CONTRACT.
31. THE AREA OF WORK WILL NOT BE WITHIN 200' OF ANY MTA STRUCTURE.
32. CONTRACTOR TO PAINT EXPOSED CONDUITS THROUGHOUT WITH COLOR TO MATCH ADJOINING
WALL OR CEILING.
33. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WORK WITH ALL SUB-CONTRACTORS
AND APPLICABLE TRADES.
34. WORK SHALL BE IN ACCORDANCE WITH MANUFACTURER'S LATEST STANDARD RECOMMENDATIONS.
35. COORDINATE OPENING LOCATIONS AND SIZES WITH MEP DRAWINGS.
36. CONTRACTOR SHALL COORDINATE LOCATION OF EXISTING LIGHT FIXTURES, MEP DUCTWORK,
PIPING, CONDUITS, ETC. WITH NEW WORK.
37. THE CONTRACTOR SHALL PROVIDE RIGID AND SOLID DUST PARTITIONS CLOSING OFF WORK AREA
FROM BALANCE OF OCCUPIED SPACES WITHIN THE EXISTING BUILDING.
38. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL MEANS AND METHODS OF CONSTRUCTION AND
PROVIDE SAFEGUARDS TO INSURE SAFETY TO THE PUBLIC FOR THE DURATION OF THE PROJECT.
39. WORK SHOWN OR REFERENCED TO ON ONE DRAWING SHALL BE PROVIDED AS THOUGH SHOWN ON
ALL DRAWINGS. WHENEVER AN ITEM IS SPECIFIED AND/OR SHOWN ON THE DRAWINGS BY DETAIL OR
REFERENCE IT SHALL BE CONSIDERED TYPICAL FOR OTHER ITEMS WHICH ARE OBVIOUSLY
INTENDED TO BE THE SAME, EVEN THOUGH NOT SO DESIGNATED OR SPECIALLY NAMED BUT DO
SERVE THE SAME FUNCTION.
40. IF THE CONTRACTOR DISCOVERS ASBESTOS OR ANY OTHER HAZARDOUS MATERIALS THE
CONTRACTOR SHALL IMMEDIATELY NOTIFY THE AUTHORITY'S REPRESENTATIVE AND SHALL
IMMEDIATELY STOP DISTURBING THE HAZARDOUS MATERIAL.
41. CONTRACTOR SHOULD INCLUDE PER EACH REMOVED DEVICE 5 SF OF PLASTER REPAIR AND 50 SF
OF PAINT TOUCH UP.
42. ADDITIONAL NOTES THAT ARE APPLICABLE TO THIS PROJECT MAY BE FOUND THROUGHOUT THE
CONTRACT DRAWINGS.
SCALE: 1"=64'-0"
00 64' 128' 256'
1. SUBMIT TO THE SCA FOR REVIEW A SITE SAFETY PLAN(S) PREPARED AND SIGNED BY A NEW YORK
CITY LICENSED SITE SAFETY MANAGER. THE PLAN(S) SHALL BE COMPLETE, REFLECTING THE
ENTIRE SITE AND SHALL SHOW ANY PHASED PROTECTION.
2. THE SITE SAFETY PLAN(S) SHALL INCLUDE, BUT SHALL NOT BE LIMITED TO, NOTES, SIDEWALK
BRIDGES, FENCES, EGRESS, SCAFFOLDING, FIRE PROTECTION ETC. THEY SHOULD ADDRESS ANY
POTENTIAL INTERACTION BETWEEN THE BUILDING OCCUPANTS AND GENERAL PUBLIC AND
EXPOSURE TO THE CONSTRUCTION PROCESS.
3. SEE SPECIFICATION SECTION S01535 FOR DETAILS.
4. NO WORK IS TO PROCEED UNTIL SITE SAFETY PLANS ARE APPROVED BY SCA.
5. AS A MINIMUM, PROVIDE SIDEWALK BRIDGING AROUND THE PERIMETER OF THE BUILDING AT ALL
PAVED AREAS.
SCHOOL
BUILDING
SITE: IS 252K BROOKLYN
SPECIAL INSPECTIONS REQUIRED IN ACCORDANCE WITH CHAPTER 17 AND THE APPLICABLE SECTIONS
OF THE NYC CONSTRUCTION CODE ARE LISTED IN THE FOLLOWING TABLES:
THE CONTRACTOR MUST NOTIFY THE ARCHITECT OR ENGINEER FOR SPECIAL INSPECTIONS AT LEAST
72 HOURS BEFORE THE SPECIFIC WORK COMMENCES.
CONCRETE- CAST-IN PLACE BC 1704.4
MASONRY BC 1704.5
SUBGRADE INSPECTION BC 1704.7.1
SUBSURFACE CONDITIONS - FILL PLACEMENT & IN PLACE DENSITY BC 1704.7.2, BC 1704.7.3
MECHANICAL SYSTEMS BC 1704.16
FUEL-OIL STORAGE AND FUEL-OIL PIPING SYSTEM BC 1704.17
HIGH-PRESSURE FUEL GAS PIPING (WELDING) BC 1704.19
STRUCTURAL STABILITY- EXISTING BUILDINGS BC 1704.20.1
EXCAVATION- SHEETING, SHORING AND BRACING BC 1704.20.2
HEATING SYSTEMS BC 1704.25
CHIMNEYS BC 1704.26
FIRE-RESISTANT PENETRATIONS AND JOINTS BC 1704.27
POST-INSTALLED ANCHORS (BB# 2014-018, 2014-019) BC 1704.32
CONCRETE SAMPLING AND TESTING TR2 ONLY BC 1905.6, BC 1913.10
THE "CONTRACTOR" SHALL BE RESPONSIBLE FOR THE FOLLOWING BUILDING DEPARTMENT FORM:
CONCRETE DESIGN MIX - TR3
PROGRESS INSPECTIONS REQUIRED IN ACCORDANCE WITH CHAPTER 1 OF THE 2014 NYC BUILDING
CODE AND THE APPLICABLE SECTIONS OF THE NYC CONSTRUCTION CODE ARE LISTED IN THE
FOLLOWING TABLES:
THE CONTRACTOR MUST NOTIFY THE ARCHITECT OR ENGINEER FOR PROGRESS INSPECTIONS AT
LEAST 72 HOURS BEFORE THE SPECIFIC WORK COMMENCES OR REQUIRES INSPECTION.
THE "AUTHORITY" SHALL BE RESPONSIBLE FOR THE FOLLOWING PROGRESS INSPECTIONS:
ENERGY CODE COMPLIANCE INSPECTIONS BC 110.3.5
1. ALL WORK IS TO CONFORM TO ALL APPLICABLE REQUIREMENTS OF LOCAL GOVERNING CODES,
HEALTH CODE, FIRE DEPARTMENT REGULATIONS, NBFU AND UTILITY CODES, OSHA CODES AND
NEW YORK CITY BUILDING CODE.
2. DURING CONSTRUCTION, TEMPORARY BAFFLES TO SEAL OPENINGS TO PREVENT DUST AND DIRT
FROM FILTERING INTO OCCUPIED AREAS ARE TO BE PROVIDED BY THE CONTRACTOR.
3. ALL DEBRIS REMOVED FROM THE SITE SHALL BE DISPOSED OF IN A LEGAL MANNER. ALL DEBRIS
SHALL BE STORED IN APPROPRIATE CONTAINERS AND THE SITE SHALL BE MAINTAINED IN A
SANITARY AND SAFE CONDITION. REFER TO SPEC SECTIONS 02070 AND S1900 FOR BALANCE OF
INFORMATION.
4. ALL EXISTING ELECTRICAL LINES, ETC. WHICH ARE TO BE REMOVED DURING DEMOLITION MUST BE
VERIFIED BY THE CONTRACTOR AS PER ITS USE, DESIGNATION AND LOCATION (IF NECESSARY).
5. ALL EQUIPMENT TO BE REMOVED AND REINSTALLED. ASSURE IT IS IN WORKING CONDITION AND
SHALL BE REINSTALLED IN SAME WORKING CONDITION. CONTRACTOR TO ADVISE IF OTHER
CONDITION FOUND.
6. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR PROTECTION OF ROOFING AT ALL TIMES
DURING THE WORK OF THIS CONTRACT. THE CONTRACTOR SHALL PROTECT CUT PORTIONS OF
THE ROOF. REMOVE TEMPORARY PROTECTION PRIOR TO INSTALLATION OF BASE SHEETS.
7. CONTRACTOR TO KEEP PHOTOGRAPHIC RECORDS AND DOCUMENT EXISTING CONDITIONS OF
AREAS OF WORK AND IMMEDIATE ADJACENT AREAS AND ANY AREAS AFFECTED BY WORK
CONTRACTOR IS RESPONSIBLE FOR APPLICATION AND PERMIT FOR THE FOLLOWING WORK:
1. TEMPORARY BOILER
2. FENCING
3. REMOVAL AND REPLACEMENT OF TREES
EAST
95
STREET
EAST
96
STREET
LENOX
ROAD
LENOX
ROAD
EAST
94
STREET
KINGSHIGTWAY
KI
05/31/2016 POST APPROVAL AMMENDMENT
2. UP
UP
UP
UP
UP
UP
UP
UP
125 BROAD STREET, NEW YORK, NY 10004
PHONE: 212-377-8400, FAX: 212-377-8410
SCA Design Manager:
D016040
Design No: Facility Code:
K 252 04/14/2016
Date:
Project:
of 64
Sheets in DOB Set:
Drawing No.:
Drawing Title:
Address:
Stanley Dahir, R.A., Director, Quality Control & Construction Support
Elan R. Abneri, P.E., Senior Director, Design Consultant Management
Architecture & Engineering
Designer:
Checked by:
Drawn by:
Project Architect/Engineer:
1084 LENOX ROAD, BROOKLYN, NY 11212
E. Bruce Barrett, R.A. LEED A.P., Vice President
Consultants:
Stacey Spann-Thom, Director, Operations Support
George D. Roussey, P.E., LEED A.P., Director, Technical Standards
Discipline Lead:
of 85
Sheets in Contract Set:
Board of Trustees
Curtis A. Harris
President & CEO
Lorraine Grillo
Emily A. Youssouf
IT IS A VIOLATION OF THE STATE EDUCATION LAW SECTION 7209 (2)
FOR ANY PERSON TO ALTER AN ITEM IN ANY WAY UNLESS SUCH
PERSON IS ACTING UNDER THE DIRECTION OF A LICENSED
PROFESSIONAL ENGINEER, AND THE ENGINEER STAMPS SUCH
CHANGES
IS 252K
BOILER REPLACEMENT
CLIMATE CONTROL
Lot # 37BLOCK # 4669
Key Plan:
EAST95THSTREET
PLAY YARD
I.S. 252K
EAST94THSTREET
LENOX ROAD
COURT
YARD
RevisionDateNo.
Scale: 1/4" = 1'-0"
CELLAR PARTIAL PLAN1
M301
00 4' 8' 16'
C
M302
B
M302
A
M302
05/31/2016 POST APPROVAL AMMENDMENT
3. 125 BROAD STREET, NEW YORK, NY 10004
PHONE: 212-377-8400, FAX: 212-377-8410
SCA Design Manager:
D016040
Design No: Facility Code:
K 252 04/14/2016
Date:
Project:
of 64
Sheets in DOB Set:
Drawing No.:
Drawing Title:
Address:
Stanley Dahir, R.A., Director, Quality Control & Construction Support
Elan R. Abneri, P.E., Senior Director, Design Consultant Management
Architecture & Engineering
Designer:
Checked by:
Drawn by:
Project Architect/Engineer:
1084 LENOX ROAD, BROOKLYN, NY 11212
E. Bruce Barrett, R.A. LEED A.P., Vice President
Consultants:
Stacey Spann-Thom, Director, Operations Support
George D. Roussey, P.E., LEED A.P., Director, Technical Standards
Discipline Lead:
of 85
Sheets in Contract Set:
Board of Trustees
Curtis A. Harris
President & CEO
Lorraine Grillo
Emily A. Youssouf
IT IS A VIOLATION OF THE STATE EDUCATION LAW SECTION 7209 (2)
FOR ANY PERSON TO ALTER AN ITEM IN ANY WAY UNLESS SUCH
PERSON IS ACTING UNDER THE DIRECTION OF A LICENSED
PROFESSIONAL ENGINEER, AND THE ENGINEER STAMPS SUCH
CHANGES
IS 252K
BOILER REPLACEMENT
CLIMATE CONTROL
Lot # 37BLOCK # 4669
Key Plan:
EAST95THSTREET
PLAY YARD
I.S. 252K
EAST94THSTREET
LENOX ROAD
COURT
YARD
RevisionDateNo.
Scale: 3/8" = 1'-0"
SECTION C3
M302
Scale: 3/8" = 1'-0"
SECTION A1
M302 Scale: 3/8" = 1'-0"
SECTION B2
M302
00 2'-8" 5'-4" 10'-8" 00 2'-8" 5'-4" 10'-8"
00 2'-8" 5'-4" 10'-8"
05/31/2016 POST APPROVAL AMMENDMENT